How Much Does It Cost to Build a Swimming Pool in Alicante?


A private concrete pool in the province of Alicante typically costs between about €13,000 and €28,000, depending on size and finish. According to idealista’s 2026 price guide, a 6×3 m concrete (obra) pool falls in the €13,000–27,000 range, an 8×4 m gunite pool in the €18,000–28,000 range, and infinity pools go beyond €40,000. The headline price is rarely the final one: ground conditions, the works licence, electrics and landscaping decide where in that range you land. At URU Reformas we build private pools in Torrevieja and the Vega Baja, and this guide sets out what the numbers are made of so you can read a quote properly.
Key Takeaways
A 6×3 m concrete pool ranges from €13,000 to €27,000 and an 8×4 m gunite pool from €18,000 to €28,000, according to idealista’s 2026 guide.
Ground conditions are the biggest hidden variable: excavating rock instead of soil can add €2,000–15,000.
Licence, pool electrical board, spoil removal and landscaping are often missing from a first quote, so ask for a phased quote that lists them.
Running costs for a standard pool come to roughly €600–1,200 a year, and must be budgeted alongside the build.
A pool in Alicante needs a works licence, and processing times in some municipalities run to several months, so plan the calendar before the price.
Table of Contents
What a pool costs in Alicante: the price bands
The cleanest way to start is by size and construction type, because these two choices fix the largest share of the budget.
Pool type or size | Typical 2026 price range | Source |
6×3 m concrete (obra) pool | €13,000–27,000 | |
8×4 m gunite pool | €18,000–28,000 | |
Infinity pool | Over €40,000 | |
Construction and installation only, all types | €4,000–32,000 |
The spread is wide because “a pool” can mean very different things. A compact plunge pool with a simple liner finish sits at the bottom of the scale. A larger pool with a deep end, a built-in step area, a salt system and decorative tiling sits near the top.
Price per square metre
Cuantomecuesta’s April 2026 breakdown gives per-square-metre guides for the construction itself: roughly €400/m² for a prefabricated shell, about €500/m² for a liner pool and about €650/m² for a poured concrete pool. These are construction-only figures. They exclude the licence, filtration, lighting, access and the surroundings, which is why a price per square metre alone never tells you the cost of the finished pool.

A real homeowner’s budget
Idealista’s guide includes a homeowner’s reported budget: €12,665.97 including 21% VAT for the pool works, plus a works licence of about €800, for roughly €13,460 all-in. It is a useful reference for a modest pool built on straightforward ground. Treat it as the lower end of what is realistic, not as the average.
How size, type and materials change the price
Every pool quote is the sum of a few choices. Understanding them lets you compare two quotes on the same basis.
Size and depth
Size is the factor with the most weight, but depth counts as much as the surface area. More depth means more excavation, more spoil to remove, thicker walls and more water. A shallow family pool of 6×3 m and a deeper 8×4 m pool with a diving end are different projects, which is why the price bands above overlap so much.
Concrete, gunite, liner or prefabricated
Poured or sprayed concrete (obra, gunite): the most flexible option, because the shape, depth and steps are designed for your plot. It carries the highest per-square-metre figure in the 2026 data, and it is the type used for larger and custom pools.
Liner pools: a structural shell finished with a PVC membrane, priced in the middle of the range.
Prefabricated shells: the lowest per-square-metre figure, but the shell must be delivered to the plot, which makes access an issue on many urbanisation plots.
We compare the two most common routes in more detail in our guide to concrete versus fibreglass pools in Spain, including site risks and permits.
Equipment and finishes
Cuantomecuesta’s 2026 breakdown prices the filtration and pump system at €1,500–3,500, with a salt chlorination system at €2,500–3,500. LED lighting runs from nothing up to €1,000, and steps and accessories from €200 to €1,500. A cover or enclosure can add anything from zero to €8,000. These items are where a basic pool becomes a well-equipped one, and they explain why a pool of the same size can differ by several thousand euros between two quotes.

What most first quotes leave out
The difference between the quote and the final bill rarely comes from the shell. It comes from items that were not priced at the start. Motor de Presupuestos’ 2026 budgeting guide highlights four.
Ground conditions. Excavating in rock rather than soil can add €2,000–15,000. The soil on your plot is the single largest unknown until it is opened up.
The pool electrical board. A board with 30 mA differential protection costs €500–2,000 and is often omitted from quotes.
Spoil removal. An 8×4 m pool generates 50–100 tonnes of spoil, and taking it away costs €1,000–3,000.
Everything around the pool. Lighting, outdoor showers, landscaping, paving and shade structures are frequently excluded, and they are where final budgets diverge most.
Pro Tip: Ask for a written clause that says how excavation is priced if rock is found, and for the electrical board and spoil removal to appear as separate lines. A quote that names them is a quote you can compare.
Access matters too. A plot reached through a narrow gate or up a steep slope may need smaller machinery or manual excavation, which raises the labour cost. Mention access, gradients and neighbouring walls when you request a quote so that it is priced for your plot.
Licence and permits: cost and timing
A pool needs a works licence from your town hall. Idealista reports that licences and permits in Spain average 4–6% of the budget, typically around €1,000, depending on size, location and whether the work counts as major works (obra mayor) or minor works (obra menor). Cuantomecuesta puts the licence at €300–1,500, with a technical project adding €500–1,500 in some regions.
The bigger issue is time. According to a 2026 overview of Alicante works licences, processing times for major works run from two to four months in smaller municipalities and from four to seven months in places such as Alicante city, Jávea and Altea. The same overview notes that a buried pool generally needs a major-works licence with a project signed by a competent technician, while small removable pools may be treated as minor works depending on the town. Because the rules and timings differ by municipality, check the requirements with your own town hall before you commit to a start date.
For a wider view of what each type of work needs, see which renovation permits are required in Alicante.
Why this matters for the calendar
If you want to swim next summer, the licence stage is the part that decides the start date, not the construction itself. Owners who live abroad for part of the year should plan the application well ahead of the season, so that digging begins when the licence is granted and not months later.
A worked budget example
Here is how the components can add up for an 8×4 m pool, using only the published ranges above. It is an illustration of how to read a budget, not a quote.
Line | Range used |
Pool construction (8×4 m gunite) | €18,000–28,000 (idealista) |
Pool electrical board | €500–2,000 (Motor de Presupuestos) |
Spoil removal | €1,000–3,000 (Motor de Presupuestos) |
Works licence | around €1,000 (idealista) |
Possible rock excavation | €2,000–15,000 if found (Motor de Presupuestos) |
Without rock, the added lines come to roughly €2,500–6,000 on top of the construction figure. With rock, the total can rise considerably more. That is why we recommend treating the first number you hear as a starting point and asking for a phased, itemised quote before deciding.
Running costs after the build
A pool is a purchase and a yearly commitment. Fotocasa Life’s May 2026 guide puts the total cost of keeping a standard pool in Spain at €600–1,200 a year. It adds up chemicals, pump electricity at around €36 a month, water and seasonal clean-ups. Per item, it lists chlorine at €150–200 a year, pH regulation at about €100 a year, anti-algae and fungicide treatments at about €200 a year, and refilling a 40 m³ pool at €100–200 every few years.
CalculaBien’s 2026 estimate is €630–1,300 a year, with a further €800–1,500 a year if you hire weekly professional maintenance. The filtration pump is the largest electricity consumer, so the equipment you choose at build stage affects your bills for years. That is one more reason to settle the specification of the pump and the cover before construction, not after it.
Spend the budget in the right order
If your budget is fixed, this order protects it:
Fix the shell, the depth and the ground work first. These are expensive to change once the excavation is done.
Specify the equipment at the outset. Retrofitting a salt system, lighting or a better pump later costs more than installing them during construction.
Price the surroundings in the same document. Paving, steps, outdoor showers and shade belong to the same project, and the pool is not finished without them.
Keep a contingency for the ground. Because rock and soil conditions are uncertain until excavation, a reserve avoids stopping work halfway.
Plan the licence before the season. A month lost in the licence queue is a month of summer lost.
Our perspective
A pool quote is only as good as its list of what is included. When we price a pool, we start with the plot: the soil, the access, the slope and where the electrical supply and the drainage will run. Those facts decide the price more than the pool’s dimensions do, and they are the first things that go missing in a hurried estimate. Our approach is to manage the work as one project, with qualified professionals, guaranteed pricing, deadlines and quality, and with insurance and regulatory compliance from start to finish. We prepare free, detailed, phased quotes, so that you can see the excavation, the structure, the equipment and the finishes as separate stages and not as a single figure. For owners who live abroad, a pool is a project you cannot visit every week. That is why we agree the stages, the payment schedule and the deadlines in the contract, and why we keep you informed with photo and video updates while the work progresses. URU Reformas
Get a quote for your plot
We build private swimming pools as part of our construction service in Torrevieja and the Vega Baja, and we can also take on the paving, terrace waterproofing, plumbing and electrical work around the pool within the same project. Our consultations are free and our quotes are detailed and phased, so you see what each stage covers. You can read about our swimming pool and new-build service or contact us with the address of your plot and the size you have in mind.

If the pool is part of a larger plan, such as a new house, our guide to how new home construction works on the Costa Blanca explains the sequence, and our work page shows completed projects.
FAQ
How much does a small pool cost in Alicante?
For a 6×3 m concrete pool, idealista’s 2026 guide gives a range of €13,000–27,000, and the homeowner budget it reports came to roughly €13,460 including licence and VAT. Where you fall in that range depends on depth, equipment and the condition of your ground.
Do I need a licence to build a pool in Alicante?
Yes, a buried pool generally needs a works licence from the town hall, and in many cases a project signed by a competent technician. Requirements and processing times differ by municipality, so confirm them with your own town hall. We can guide you through the process as part of a pool project.
How long does it take to get permission?
According to a 2026 overview of Alicante licences, major works take about two to four months in smaller municipalities and four to seven months in larger ones such as Alicante city. Check the current timings with your town hall before fixing a start date.
What does it cost to run a pool each year?
Fotocasa Life’s 2026 guide estimates €600–1,200 a year for a standard pool in Spain, covering chemicals, pump electricity, water and seasonal clean-ups. A variable-speed pump and a thermal cover are the usual ways to keep the electricity and chemical share down.
What is most often missing from a pool quote?
The pool electrical board, spoil removal, the extra cost of rock excavation and the surroundings, such as lighting, paving and showers. Asking for these as separate lines makes quotes comparable.