How Renovation Payments Are Usually Structured in Spain


Most renovation contracts in Spain are paid in three parts: an advance when the job is agreed, one or more payments as the work progresses, and a final payment once you have reviewed the finished result. Spanish law does not fix those percentages, so the schedule is whatever you and the contractor write into the quote. This guide explains the common patterns, the protections worth asking for and the checks that matter when you are not on site.
Key Takeaways
Madrid’s consumer authority reports that companies commonly ask for 30–40% at the start and a final payment, sometimes with a mid-work instalment.
The consumer organisation OCU advises keeping the first payment to 20–30%, paying further sums as the work advances and keeping about 30% back until completion.
Spanish law lets you and the contractor agree any schedule, so the quote or contract is your real protection. Put amounts, milestones, dates and changes in writing.
Ask for an invoice for each payment, expect 21% VAT in most cases (10% only under set conditions) and do not pay large sums in cash.
Tie payments to finished stages, not to calendar dates, and consider a retention of around 5% until final handover.
Table of Contents
What the law says, and what it leaves to you
There is no statutory deposit in Spain for renovation work. Under Article 1599 of the Civil Code, unless the parties agree otherwise or local custom says otherwise, the price of the work is payable when the finished work is delivered. In practice almost nobody works that way, because a contractor has to buy materials and pay labour before anything is handed over. The same legal text points to the contractor’s right to retain the work until it is paid, which is one reason the parties set out a different schedule in advance.
A legal commentary from DLA Piper notes that few legal provisions are implied into construction contracts in Spain. For a homeowner the consequence is simple: whatever is not written down is hard to enforce. Payment terms are a matter of negotiation, and the written quote (presupuesto) or contract is where they live.
The usual structure: advance, stages, final payment
The Comunidad de Madrid consumer guidance says companies commonly request 30–40% at the beginning and a final payment, and that some also ask for a payment halfway through. The consumer organisation OCU takes a more cautious line: limit the initial payment to 20–30%, make later payments as the work progresses, and pay about 30% when the work is completed to your satisfaction.
The two figures overlap more than they appear to. A typical schedule for a medium-sized job looks like this:
Payment | Trigger | Typical share |
Advance | Signed quote or contract, before materials are ordered | 20–40% |
Stage payment(s) | Completion of a defined phase, such as strip-out, first-fix plumbing and electrics, tiling | Balance of the middle of the project, split across one or more stages |
Final payment | Handover after you have checked the work | Around 30%, or less if a retention is agreed |
These are the ranges the consumer sources describe, not fixed rules and not a quote from us. A small bathroom job may be two payments. A full renovation of a villa may have five or six, one per phase.
Why the advance exists
The advance is not a fee for signing. It covers materials ordered specially for you (kitchen units, sanitary ware, windows), the contractor’s scheduling of a team and any initial site protection. It is reasonable for it to be proportionate to those early costs. If a contractor asks for a large share before any materials are bought or work begins, ask what it pays for.

Paying by stage, not by date
The cleanest schedules link each payment to a visible, checkable milestone. “On completion of first-fix plumbing and electrics, with pressure test passed” is easy to verify. “On 15 March” is not, because work slips for reasons on both sides. Stage-based payment also keeps the contractor’s cash flow healthy, which is in your interest: a team that is paid fairly at each phase has no reason to leave your site to cover costs on another.
Worked example: a bathroom and kitchen renovation
To show how stages work, here is an illustrative structure, with invented round numbers purely for arithmetic, for a job quoted at €20,000 before VAT. It is not a client price and not a market average.
Advance, 25%: €5,000. Paid on signing, covers the order of sanitary ware, units and tiles.
Stage one, 25%: €5,000. Strip-out finished, new plumbing and electrical routes in place and tested.
Stage two, 20%: €4,000. Tiling and plastering complete.
Stage three, 15%: €3,000. Fitted units, sanitary ware and carpentry installed.
Final payment, 15%: €3,000. Paid at handover, after you have gone through a snagging list and the contractor has corrected what is on it.
If you also agree a retention, a proportion such as 5% is held back from each payment instead and released at final handover. Whichever shape you choose, the percentages should add to 100% and appear in the contract with the milestone that triggers each one.
Retentions and defect guarantees
On larger projects, a retention is a recognised tool. OCU says that for large projects a 5% retention may be agreed. DLA Piper describes a defects guarantee of about 5% of the construction price retained from each payment and returned after final handover.
The idea is straightforward. Small defects often appear in the first weeks: a leak under a new basin, a door that rubs, a patch of paint that lifts. A retention gives both sides a reason to resolve them quickly and without argument. Write down the release date or condition, for example “released within 14 days of signed handover, less the cost of any items on the snagging list not yet corrected”.
Pro Tip: Agree the snagging process before work starts. A short list, a date for the walk-round and a date for corrections turns a potential dispute into a routine step.
What the written quote should contain
The Madrid guidance says a written quote works as a work order and should identify the company and the client, describe the work, materials and prices, include approximate start and end dates, and state its validity and the warranty period. It should also include the contractor’s registration number, contact details, a breakdown of labour and materials and what taxes are included. Use it as a checklist:
Parties and registration: company name, tax ID, contact details.
Scope: every room and trade, with materials specified by type or brand, not “good quality tiles”.
Price breakdown: labour and materials separated, with VAT shown.
Payment schedule: percentages or amounts, each tied to a milestone.
Dates: an approximate start and end, and what happens if they move.
Validity and warranty: how long the price holds and how long the work is guaranteed.
Changes: how variations are priced and approved.
On changes, the same guidance says modifications needed for hidden defects must be documented and signed by both parties before the work goes ahead. Older Spanish properties often reveal damp, outdated wiring or unsound substrates once walls are opened, so agree in advance how these will be handled. For a deeper look at how to size a budget and a contingency, see our guide on how much to budget for a home renovation in Spain.
Delay penalties
OCU recommends including a delay penalty in the contract and actually requiring it when delays occur. A clause that states a daily or weekly amount, and which delays are excluded (for example, those caused by your own late decisions or by a variation you requested), is more useful than a vague promise to finish “around June”.
Invoices, VAT and cash
Request a detailed invoice after the work that shows materials, labour and VAT, as the Madrid consumer guidance advises. The same source gives the standard VAT rate for renovation work as 21%. A 10% rate may apply to work in a habitual residence at least two years old when the contractor is a natural person, and where you supply materials, they must not exceed 40% of the total value of the work. Those conditions are specific, so ask the contractor and, if the sum is large, your tax adviser (asesor fiscal) which rate applies to your property before you sign. A second home or a rental apartment is not automatically a habitual residence.

Cash deserves a separate warning. OCU states that cash payments of 1,000 euros or more in professional or business transactions are prohibited by law. Pay by bank transfer, quote the invoice or quote number in the reference and keep the confirmation. A payment trail protects you if there is later a warranty claim, a dispute or a resale where the buyer asks to see what was done.
Paying safely when you are abroad
Many of the owners we work with live outside Spain, so the payment schedule has to work without you standing on site. The checks that matter are practical ones:
Pay only against evidence. Before each stage payment, ask for dated photos or a short video of the finished phase, taken from the same angles each time so you can compare.
Agree who approves what. If someone else visits on your behalf, such as a family member or an architect, name them in the contract and say whether they may approve milestones.
Keep transfers traceable. Pay from your own account to the company’s business account named on the quote and invoice, not to a personal account or a third party.
Ask for an invoice per payment. A running record is easier to reconcile from another country and useful for your own tax filings at home.
Plan currency and transfer time. Stage payments can be delayed by international transfers, so agree how many working days a payment may take to arrive before it counts as late.
Keep the written trail. Confirm decisions by email, since messaging threads are hard to use if there is a disagreement.
Our guides on renovating a Spanish property from abroad and what foreign homeowners should know before renovating in Spain cover permits, approvals and communication in more detail.
What to do if work is late, incomplete or defective
The advice from OCU follows a clear order. Review the work, ask for corrections, and complain in writing about problems or unjustified delays. If that does not resolve it, contact a consumer information office. Arbitration is available if the contract states that the company belongs to the Consumer Arbitration System.
Two habits make this easier. First, do not pay a stage until the work in that stage is done, because withholding a payment that is not yet due is simply following the contract. Second, keep every complaint dated and in writing. Verbal agreements on site are normal and often friendly, but they are very hard to prove.
Our perspective
Payment structure is where a renovation is won or lost. In our experience of residential work in Torrevieja and the Vega Baja, projects run best when the schedule is set out before the first tool comes out of the van: a modest advance, payments tied to completed phases and a final payment at handover. That is why we give free, detailed quotes that are phased, so that each stage of the work and its cost are visible before you commit. Our approach is built around guaranteed pricing, deadlines and quality, with insurance and regulatory compliance managed from start to finish, and we manage every trade on one contract, so you deal with one party, not five. For owners who live abroad, we believe the right answer is transparency: clear communication, photographic updates as each phase closes and invoices that match the quote. Humidity, salt air and older construction are common on this coast, so we also specify hidden-work items early and agree changes in writing before they are carried out. URU Reformas
Plan your renovation payments with us
If you are comparing quotes, put the payment schedule next to the scope and the dates, since the three belong together. We provide free consultations and detailed phased quotes for full and partial renovations, kitchens, bathrooms, waterproofing, plumbing, electrical work, carpentry and painting across Torrevieja and the Vega Baja.

To see what we cover, visit our full renovation services or contact us for a quote with the payment stages set out. If you are still choosing a builder, our shortlist guide on how to choose a renovation company in Torrevieja explains what to check first.
FAQ
How much deposit should I pay a builder in Spain?
There is no legal figure, so it is negotiated. Madrid’s consumer authority says companies commonly ask for 30–40% at the start, while OCU advises limiting the first payment to 20–30%. Ask what the advance pays for and make sure it is stated in the contract.
Do I have to pay the full price when the work is finished?
Under Article 1599 of the Civil Code, the price is payable on delivery unless you agree otherwise, but most contracts set stage payments instead. If you agree a retention, usually around 5%, the balance is released after final handover and any corrections.
Can I pay a renovation in cash?
Not for large amounts. OCU states that cash payments of 1,000 euros or more in professional transactions are prohibited by law. Use a bank transfer, reference the invoice and keep the receipt.
What VAT applies to renovation work in Spain?
The general rate is 21%. According to Madrid’s consumer guidance, a 10% rate may apply to work in a habitual residence at least two years old when the contractor is a natural person and any materials you supply do not exceed 40% of the work’s value. Confirm your case with the contractor or a tax adviser.
What if the contractor delays or leaves work unfinished?
Complain in writing to the company, citing the contract and dates. If that fails, contact a consumer information office, and use arbitration if the contract says the company is part of the Consumer Arbitration System. A delay penalty clause makes this much simpler.